2020 Excellence in Environmental Engineering and Science™ Awards Competition Winner

E3S Grand Prize

Grand Prize - Design

Stormwater and Deicing Capacity Projects

Entrant: Wessler Engineering
Engineer in Charge: William J. Leber, P.E.
Location: Indianapolis, Indiana
Media Contact: Bill Leber


Entrant Profile

Wessler Engineering

Wessler Engineering is a team of water resources experts who help local committed leaders make sure their water is safe, managed, and future-proof. Wessler Engineering was the Prime Consultant and Lead Designer on the Indianapolis Airport Authority's Stormwater and Deicing Capacity Projects. Wessler provided lead design, construction administration and construction observation.

When Wessler was awarded its contract, IAA made it clear this high-profile project was being performed for a client with unrealistic expectations and an impossible schedule. Wessler assembled a team and served as Prime for eighteen partner firms. To achieve the IAA objectives, multiple sites and disciplines were designed simultaneously.

Eighteen (18) subconsultants were selected to meet the Indianapolis Airport Authority's minority and diversity goals. Subconsultants provided services in the following areas: structural, electrical, mechanical design and construction administration; FAA and airspace coordination and permitting; environmental and regulatory coordination and permitting; modeling; construction cost estimating; materials testing; hydrologic and hydraulic engineering; geotechnical engineering; and survey. Weekly meetings between IAA, the design team and construction manager determined the attitude and mindset for the entire design and construction effort. Value engineering and construction sequencing were considered paramount and throughout the design phase, ideas were vetted, and decisions made quickly; the design contract was awarded in August 2017 and the first bid documents were issued in February 2018.

Project Description

In January 2018, FedEx announced a seven-year, $1.5 billion hub expansion at their Indianapolis facility. In anticipation of this announcement, Indianapolis Airport Authority (IAA) selected Wessler Engineering to deliver major modifications of the Stormwater and Deicing facilities.

In concept this project is simple; collect and store stormwater and discharge "clean" water slowly to local streams in compliance with the airport NPDES permit or "contaminated" water to the Indianapolis sanitary system. Existing storm sewers convey airport runoff to large open-air basins located on land adjacent to FedEx needed for their expansion plans.

Airspace security, a 150-year old, 400-gravesite cemetery and large-diameter tunnels are not typical issues related to a stormwater facility but were all considerations of this project. The east project: Hanna Basin and Seerley Creek Facility, included two large diameter 750-foot long tunnels under I-70, an enclosed 10-million-gallon storage and junction chamber and 7 mgd pumping station, 95 million gallons of new storage in three reinforced polypropylene geomembrane lined basins and three large pumping stations (a 40 mgd station used to fill the basins upper portion and transfer stored water between basins, a 13 mgd station to pump contaminated water to the municipal collection system and an 8.5 mgd station to pump clean water back to the Seerley Creek Facility for release). A new West Basin, to handle runoff from the west side of the airport, includes another 5-million-gallon lined basin and 7 mgd pump station along with a 24-inch force main under I-70 and nearly 13,400 feet back to the Hanna Basin.

Flow and fill sequences are programmed, monitored and managed via real-time SCADA including the potential to automate sluice gates and pumps. The design allows IAA personnel to override the system to manually manage runoff streams based upon weather, basin levels, flow rates and readings obtained from strategically placed TOC analyzers.

Much of the design incorporated "tried and true" technologies configured for new objectives. Equipment selection mandated durability in harsh environments and was upsized to address the extreme sizes of this project. Sustainable design goals included segregating runoff streams to provide recycling opportunities if/when it becomes cost-effective. Energy efficiency was another sustainability goal. Peak runoff rates to the Seerley Facility can exceed 170 CFS (110 MGD) and a single storm can create 25 million gallons of runoff. Instead of pumping, the 78-inch pipe from Hanna fills the first 15 feet of the 30-foot deep Seerley basins by gravity with pumps filling the remainder. For many rainfall events, no pumping will be required aside from the discharge to the sanitary collection system.

Engineering costs accounted for approximately half a percent of the of total FedEx project budget, yet planning and delivery were considered critical to attain the unrealistic and impossible timeline.

Integrated

Air: The IAA deicing runoff basins are miles apart. The Deicing Capacity Projects included a SCADA system for remote monitoring and operation of the system, thereby reducing the number of trips by car and the associated emissions.

Water: The runoff streams are segregated and managed separately in order to maximize clean releases to the receiving stream and minimize the volume of contaminated runoff sent to the sanitary sewer system.

Land: The basin grading plan minimized spoils. Excavated material was used to build the embankments. No clean fill was sent to a landfill. A soil stockpile was formed for future use at the airport.

Quality

IAA plays a large role supporting central Indiana socially, environmentally and economically. Early in the design phase, a Sustainability Charette was held with the stated purpose being "to holistically identify priorities, generate sustainability ideas and assess their feasibility based on the specific challenges/opportunities for the project".

Throughout the design and into construction, aspects of this project were vetted with IAA staff and ultimately decisions were made which considered schedule and perception more than simply cost. Significant thought went into how this system would be operated both at inception and into the future when regulations might change.

Original and Innovation

  • Air mixing is regularly incorporated into water and wastewater treatment plant projects through coarse or fine bubble aeration. This project employed large bubble compressed air mixing, a modified implementation of an established technology. It allowed two goals to be accomplished: 1) provided complete mixing of the runoff in each basin, and 2) created a waterfowl deterrent. Mixing was considered crucial.
       Geese and jet engines do not mix; thus, waterfowl deterrence is of utmost importance. Alternatives were considered before concluding the disturbed surface tension from the air-mix system will make the basin(s) undesirable for birds to land. The air-mix system is the first ever used as a waterfowl deterrent and largest ever fabricated by EnviroMix, the vendor for this project and an industry leader.
  • The junction structure is designed not only to control the rate of discharges to Seerley Creek, it is also configured with slide gates and weirs that enable IAA to alter their operation to save energy during non-deicing season.

Complexity

  • Design complexities included segregating flow stream and storing clean versus contaminated runoff separately; and maximizing gravity flow to reduce the total system energy requirement.
  • Decommissioning a 43-million-gallon basin while keeping it operational during the winter of 2018-2019 was addressed with a "Control of Water" plan, which facilitated construction in multiple phases while keeping ADF laden runoff out of the receiving stream.

Contribution to Social or Economic Advancement

At its core, this is an environmental engineering project with sustainability a key tenant. As temperatures dip below freezing, aircraft deicing fluid (ADF) is applied to remove and/or prevent ice from forming on planes. This project was designed to protect the downstream receiving streams and groundwater.

  • Sustainable design goals for the project included segregating runoff streams, providing recycling opportunities, and minimizing pumping.
  • Flow scenarios and fill sequences are managed and automated via SCADA including the potential to automate the operation of sluice gates and pumps. The design allows IAA personnel to override the system to manually manage runoff streams based upon weather, basin levels, flow rates and readings obtained from strategically placed TOC analyzers.

Click images to enlarge in separate window.

E3S Photos E3S Photos

Aerial view of Hanna basins

108" Tunnel under I-70

E3S Photos E3S Photos

One of the 10 Pumps in the Hanna North Structure

Inside the 10MG Seerley Tank

E3S Photos E3S Photos

5MG West Facility Basin

Hanna East air mixing piping

E3S Photos E3S Photos

Concrete placement at Seerley Creek PT Deck

Launch Pit for 108" and 87.5" Tunnels

E3S Photos E3S Photos

Hanna North Structure and Enviromix Air System

E3S Photos E3S Photos

Online TOC analyzers and Refrigerated Samplers are used to manage the runoff


Click here to return to the list of 2020 winners.
 

Our Partners

ABET AEESP AIChE APHA APWA ASCE ASEE AWMA  Black and VeatchCDM Smith CESB DSWA EESF Geosyntec LACSD ladwp   MWDSC nacwa naem    OCSAN PDH Online SCS Engineers Stanley ConsultantsSWANA usaidis uswaterpartnership WEF